TierPoint Sioux Falls Data Center

TierPoint Sioux Falls Data Center

Morrissey Engineering was retained by TierPoint for design services to upgrade their data center located in Sioux Falls, South Dakota.

Services

Features

Data Center Expansion 

  • Expansion of raised floor data center equipment space from approximately 2800 square feet to approximately 4025 SF
  • Creation of staging, storage and conference room areas to serve the data center
  • Installation of additional UPS module to increase capacity from 500VKA to 750KVA (internally redundant to 500KVA)
  • Installation of additional PDU units to serve planned additional critical load
  • Cooling for new data center space and modifications to cooling in UPS area to accommodate additional load

Data Center Modifications 

  • Replacement of existing 150KVA ups system with 500KVA UPS system (internally redundant to 250KVA)) 
  • Installation of additional PDU units to serve planned additional critical load
  • Cooling modifications for UPS area

Project

Upgrade

Location

Sioux Falls, South Dakota

Square Footage

12,075 SF
4,025 RSF SF office space

Completion Date

2010-2011 & 2015